I have created an Ad Hoc View which is pulling data from the Financial Managemnet DB to get a monthly view of Plan Cost (Forecast) vs Actual.

The results shows that the Plan Cost for a prior month (closed) has a figure of $0, even though there is a number in the Cost Plan.  Why is this happening and how can we fix it?

Link to comment
Share on other sites

  • Replies 2
  • Created
  • Last Reply

Top Posters In This Topic

Popular Days

Top Posters In This Topic

When I look at the Cost Plan in Clarity for January it shows:

Cost = 58,683

Actual Cost = $70,690

Cost Variance = $(12,007)

 

When I run the Ad Hoc view for January it shows:

Plan Cost = $0

Actual Cost = $70,690

 

My question is why is the Plan Cost in the Ad Hoc View equals $0

 

 

 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now

×
×
  • Create New...